Install, replace or remove a fireplace or a fuel-burning stove

Last updated November 9, 2023

If you wish to install a natural gas fireplace or own a pollution-emitting solid fuel-burning stove and want to replace it with a certified appliance, you must obtain a permit to do so. Find out how to obtain a permit.

A renovation permit is required to install, replace or remove a solid fuel-burning appliance (wood, coal, eco-friendly logs, pellets).

In some boroughs, this permit is also required to install, replace or remove a stove or fireplace that uses another type of fuel (fuel oil, natural gas or propane).

You are first required to have your existing chimney inspected by a chimney sweep or a professional inspector in order to ensure that it is suitable for its intended use.

Once you have received your permit and completed your work, be sure to comply with all legislation by declaring the installation, replacement or removal of your appliance.

My borough

Shows borough content for
Find a borough to filter the list of search content.

No borough selected.

A renovation permit is required to install, replace or remove:

  • a solid fuel-burning appliance (wood, coal, eco-friendly logs, pellets)
  • a stove or fireplace that uses another type of fuel (fuel oil, natural gas or propane)

Apply on line or at the permit counter. Be sure you have all documents with you.

Rules to follow

  • Concerning a solid fuel-burning appliance, only the installation of an EPA- or CAN/CSA-B415.1-certified pellet-burning appliance is authorized.
  • Appliances that use a different type of energy are authorized.
  • Any mechanical equipment must not be visible on an exterior building facade.

Fire safety standards set out under the Québec Construction Code must be met when removing or installing an appliance.

Contact the permit counter to verify the rules applicable to your situation.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building
  • $473 for a commercial, industrial, institutional or mixed-use building.

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Required documents

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner

Communication channels

Payment method

  • Credit card (MasterCard, Visa)

Point de service

555 Rue Chabanel Ouest
Suite 600
Montréal, QC H2N 2H8

Legislation

A renovation permit is required to install, replace or remove:

  • a solid fuel-burning appliance (wood, coal, eco-friendly logs, pellets)
  • a stove or fireplace that uses another type of fuel (fuel oil, natural gas or propane)

Rules to follow

The use of solid fuels is prohibited unless the device or fireplace has been certified by the U.S. Environmental Protection Agency (EPA). 

The atmospheric emission rate of the solid-fuel burning device must be less than or equal to 2.5 g/h of fine particles.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building
  • $473 for a commercial, industrial, institutional or mixed-use building.

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Required documents

Three copies of these documents:

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner
  • Photo of the wall where the fireplace is located or planned 
  • Proxy document signed by the property owner, letter of authorization from each co-owner or a resolution of the co-ownership board

Communication channels

In person

By appointment
7171 Rue Bombardier
Second floor
Montréal, QC H1J 2E9

Legislation

A renovation permit is required to install, replace or remove:

  • a solid fuel-burning appliance (wood, coal, eco-friendly logs, pellets)
  • a stove or fireplace that uses another type of fuel (fuel oil, natural gas or propane)

Apply on line or at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building
  • $473 for a commercial, industrial, institutional or mixed-use building.

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Required documents

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner

Communication channels

Payment method

  • Credit card (MasterCard, Visa)

Point de service

5160 Boulevard Décarie
Montréal, QC H3X 2H9

Legislation

A renovation permit is required to install, replace or remove:

  • a solid fuel-burning appliance (wood, coal, eco-friendly logs, pellets)
  • a stove or fireplace that uses another type of fuel (fuel oil, natural gas or propane)

Apply at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building

 

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Required documents

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner

Communication channels

Point de service

1800 Boulevard Saint-Joseph
Montréal, QC H8S 2N4

Legislation

Apply on line or at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building
  • $473 for a commercial, industrial, institutional or mixed-use building.

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Required documents

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner

Apply

Payment method

  • Credit card (MasterCard, Visa)

By appointment
55 Avenue Dupras
Montréal, QC H8R 4A8

Payment method

Click on the place to see accepted methods of payment.

Legislation

A renovation permit is required to install, replace or remove:

  • a solid fuel-burning appliance (wood, coal, eco-friendly logs, pellets)
  • a stove or fireplace that uses another type of fuel (fuel oil, natural gas or propane)

Apply online or at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building
  • $473 for a commercial, industrial, institutional or mixed-use building.

An additional fee of $3.50 applies for every $1,000 of work for the review of restoration, replacement or transformation work carried out on a part of a building visible from a public street.

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Required documents

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner

Communication channels

Payment method

  • Credit card (MasterCard, Visa)

Point de service

201 Avenue Laurier Est
Fifth floor
Montréal, QC H2T 3E6

Legislation

A renovation permit is required to install, replace or remove:

  • a solid fuel-burning appliance (wood, coal, eco-friendly logs, pellets)
  • a stove or fireplace that uses another type of fuel (fuel oil, natural gas or propane)

Apply online, at the permit counter or by phone at 311.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building
  • $473 for a commercial, industrial, institutional or mixed-use building.

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

For general information, please contact the permit counter.

Required documents

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner

Communication channels

Submit your renovation permit applications all at once (building interior, roof, doors and windows, exterior siding, projections such as stairs, balconies and terraces).

You need an account on montreal.ca to use this service.

Payment method

  • Credit card (MasterCard, Visa)

311

Outside of Montréal: 514-872-0311

Monday to Friday: From 8:30 a.m. to 8:30 p.m.
Saturday, Sunday and public holidays: From 9 a.m. to 5 p.m.

Legislation

A renovation permit is required to install, replace or remove:

  • a solid fuel-burning appliance (wood, coal, eco-friendly logs, pellets)
  • a stove or fireplace that uses another type of fuel (fuel oil, natural gas or propane)

Apply online or at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building
  • $473 for a commercial, industrial, institutional or mixed-use building.

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Required documents

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner

Communication channels

Payment method

  • Credit card (MasterCard, Visa)

Point de service

15795, boulevard Gouin Ouest
(on the 2nd floor, rear door of the citizen reception and public safety office)
Montréal, QC H9H 1C5

Legislation

Apply online or at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building
  • $473 for a commercial, industrial, institutional or mixed-use building.

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Required documents

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner

Communication channels

Payment method

  • Credit card (MasterCard, Visa)

Point de service

By appointment
6854 Rue Sherbrooke Est
Montréal, QC H1N 1E1

Legislation

A renovation permit is required to install, replace or remove:

  • a solid fuel-burning appliance (wood, coal, eco-friendly logs, pellets)
  • a stove or fireplace that uses another type of fuel (fuel oil, natural gas or propane)

Apply online or at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building
  • $473 for a commercial, industrial, institutional or mixed-use building.

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Required documents

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner

Communication channels

Payment method

  • Credit card (MasterCard, Visa)

Point de service

4241 Place de l'Hôtel-de-Ville
Montréal, QC H1H 1S4

Legislation

Apply online or at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $160.45 for a strictly residential building
  • $472.16 for a commercial, industrial, institutional or mixed-use building.

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Permit validity

The permit is valid for a period of 18 months. Work must begin within 12 months of obtaining the permit and may not be interrupted for six consecutive months or more.

Required documents

  • the title to property establishing that the applicant is the owner of the building, along with the certificate of location
  • the plans, elevations, sections, details and construction specifications required to clearly understand the construction project, its use and the use of the lot; these plans must be provided on a scale of at least 1:100
  • the various permits, certificates and authorizations required by the authorities

 If applicable :

  • a site development and architectural integration plan that respects heritage and includes the documents required under by-law 1189 concerning such plans (PIIA)

Communication channels

Payment method

  • Credit card (MasterCard, Visa)

Point de service

1431 Avenue Van Horne, 2nd floor
Montréal, QC H2V 1K9

Legislation

A renovation permit is required to install, replace or remove:

  • a solid fuel-burning appliance (wood, coal, eco-friendly logs, pellets)
  • a stove or fireplace that uses another type of fuel (fuel oil, natural gas or propane)

Apply online or at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications are $60.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Communication channels

Payment method

  • Credit card (MasterCard, Visa)

Point de service

13665 Boulevard de Pierrefonds
Montréal, QC H9A 2Z4

Legislation

A renovation permit is required to install, replace or remove:

  • a solid fuel-burning appliance (wood, coal, eco-friendly logs, pellets)
  • a stove or fireplace that uses another type of fuel (fuel oil, natural gas or propane)

Apply online or at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Required documents

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner

Communication channels

Payment method

  • Credit card (MasterCard, Visa)

Point de service

12090 Rue Notre-Dame Est
Montréal, QC H1B 2Z1

Legislation

Apply online or at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building
  • $473 for a commercial, industrial, institutional or mixed-use building.

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Required documents

  • Appliance data sheet
  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Details of chimney partition walls
  • Roof clearance

Communication channels

Payment method

  • Credit card (MasterCard, Visa)

Point de service

5650 Rue D'Iberville
Second floor
Montréal, QC H2G 2B3

Legislation

Apply online or at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Issuance period 

The issuance period for a renovation permit varies between 30 and 60 days from the date of receipt of the application.

Permit validity

The certificate is valid for a period of six months. The work must start within three months of obtaining it.

Required documents

Two copies of scale plans, including:

  • floor plans showing the placement of the fireplace and chimney
  • elevation drawings and vertical cross-section of the fireplace
  • certificate of location showing the placement of all outdoor chimney sections on the wall or rooftop
  • vertical cross-sections and details of  construction
  • data sheets attesting that the fireplace and chimney are certified

Communication channels

Payment method

  • Credit card (MasterCard, Visa)

Point de service

777, boulevard Marcel-Laurin
Saint-Laurent, QC H4M 2M7

Legislation

Apply at the permit counter or online. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Required documents

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner

Communication channels

Point de service

8400 Boulevard Lacordaire
Montréal, QC H1R 3B1

Legislation

A renovation permit is required to install, replace or remove:

  • a solid fuel-burning appliance (wood, coal, eco-friendly logs, pellets)
  • a stove or fireplace that uses another type of fuel (fuel oil, natural gas or propane)

Apply online or at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building
  • $473 for a commercial, industrial, institutional or mixed-use building.

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Required documents

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner

Communication channels

Payment method

  • Credit card (MasterCard, Visa)

Point of service

4555 Rue de Verdun
Suite 109
Montréal, QC H4G 1M4

Payment method

Click on the place to see accepted methods of payment.

Legislation

Apply online or at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building
  • $473 for a commercial, industrial, institutional or mixed-use building.

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Permit validity

The permit is valid for a period of 18 months. The work must start within 12 months of obtaining the permit and may not be interrupted for a period of six consecutive months or more.

Required documents

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner

Communication channels

Payment method

  • Credit card (MasterCard, Visa)

Point de service

800 Boulevard De Maisonneuve Est
ground floor
Montréal, QC H2L 4L8

Legislation

A renovation permit is required to install, replace or remove:

  • a solid fuel-burning appliance (wood, coal, eco-friendly logs, pellets)
  • a stove or fireplace that uses another type of fuel (fuel oil, natural gas or propane)

Apply online or at the permit counter. Be sure you have all documents with you.

Fees

Processing fees for permit applications vary based on the projected cost of the work. You will be required to pay $9.80 for every $1,000 of work.

Regardless of the amount of work, you will be required to pay a minimum:

  • $161 for a strictly residential building
  • $473 for a commercial, industrial, institutional or mixed-use building.

The projected costs must include all fees associated with the work (ex. plans, labour, equipment), taxes included.

Additional fees may apply if your building or the area in which it is located has historic value or is subject to specific architectural standards.

The fees are non-refundable.

Required documents

  • The appliance’s technical sheet
  • Professional quality scale plan
  • Cost estimate or contractor’s bid

If applicable:

  • Certificate of location in the case of the construction or installation of an outdoor chimney
  • Power of attorney from the owner

Communication channels

Payment method

  • Credit card (MasterCard, Visa)

Point de service

405 Avenue Ogilvy
Suite 111
Montréal, QC H3N 1M3

Legislation