Obstruction

Avenue Hamel between Sauriol and Fleury

Underground infrastructure work

Borough
Ahuntsic-Cartierville
View obstruction on map

Details

Planned start date
April 19, 2026
Planned end date
May 3, 2026
Obstruction schedule
24hr/day
Weekdays and weekend if necessary
Site authority
Commission des services électriques de Montréal
Work performed by Telecon

Affected Area

Avenue Hamel

Complete closure. Detours planned

On-street parking
3 free parking spaces (with or without sticker)
Pedestrian walkway
Pedestrian walkway available

Avenue Christophe-Colomb

Partial obstructions are planned. Signage showing rules to follow during construction is posted on site.

Bike path
Alternative cyclist path available
Public transport
Bus stop moved. For more information, visit the transportation company's Web site

Rue Fleury Est

On-street parking prohibitions and restrictions in effect

On-street parking
3 free parking spaces (with or without sticker)
8 paid-parking spaces : AC249, AC250, AC251, AC254, AC255, AC262, AC263, AC264
Bike path
Alternative cyclist path available
Pedestrian walkway
Pedestrian walkway available