Reconditioning and reconstruction work on water and sewer pipes will begin in Ville-Marie borough. Find worksite updates here and learn about the measures taken by the city to reduce impacts on your daily activities.
Find out more about the worksite
When?
November 2025 to October 2026
Where?
On Avenue De Lorimier, between Rue Notre-Dame and Rue Sherbrooke
On Boulevard De Maisonneuve Est, between Avenue De Lorimier and Avenue Papineau
On Boulevard René-Lévesque, between Avenue De Lorimier and rue Dorion
On rue Ontario, between Avenue De Lorimier and Rue Cartier
On Rue de Rouen, between Avenue De Lorimier and es Érables
What?
Mainly the reconditioning of water and sewer pipes by lining:
- A 600 mm water pipe under Avenue De Lorimier, between Rue Notre-Dame and Rue Sherbrooke;
- A 750 mm water pipe under Boulevard De Maisonneuve, between Avenue De Lorimier and Papineau;
- A 200 mm secondary water pipe under Rue de Rouen
- A 900 mm X 600 mm brick water pipe under Rue Ontario between Avenue De Lorimier and Rue De Bordeaux.
Work will also include:
- The construction of a new water pipe to distribute water to the Falardeau residential area
- The reconstruction of sections of 200 mm, 250 mm and 300 mm conduits at the intersection of Avenue De Lorimier and Boulevard René-Lévesque Est
- The reconditioning or replacement of valve chambers
- Related work (curb and sidewalk renewal, demolition and installation of a median strip, removal of trees and plantation of grass) on Avenue De Lorimier, between Rue Notre-Dame and Rue Sherbrooke and on adjacent streets.
Why?
Work aims to recondition water and sewer conduits that are over a hundred years old
- The 600 mm water pipe made of grey cast iron, located under Avenue De Lorimier and installed in 1892has undergone a number of breaks and leaks over the past few years. Due to these repeated incidents, it was decided the pipe would be monitored for a year, in order to follow its evolution and decay in real time. Following a verification of its state, it was taken out of commission preventively last year.
- The 750 mm water pipe under Boulevard De Maisonneuve, installed in 1901, is still in service. Its numerous breaks and leaks were recorded over the past few years. Although the pipe had been reconditioned, it broke so many times that this places it at high risk at this time.
- Given the worrisome state of the pipe and to eliminate any risk of it breaking again, the Direction du Réseau d’Eau decided to proceed with the reconditioning of the pipes in question. The work aims to significantly enhance the system’s reliability, to ensure the durability of municipal assets, and to contribute to the remediation of the city’s infrastructure maintenance deficit.
- The 900 mm x 600 mm water pipe under Rue Ontario, installed in 1875, is still in service.
- The 200 mm water pipe under Rue de Rouen, installed in 1905, is still in service.