Work on Saint-Urbain, between des Pins and Prince-Arthur
This Plateau-Mont-Royal project involves the reconstruction of water and sewer pipes. Work is also planned to ensure the safety of pedestrians, cyclists and motorists.
It will be carried out in two phases: infrastructure work in the summer and fall of 2024, and finishing work in the spring and summer of 2025.
All you need to know
Where?
Rue Saint-Urbain, between Avenue des Pins and Rue Prince-Arthur
When?
August 2024 to July 2025
What?
In 2024, work will begin at the intersection of Rue Saint-Urbain and Rue Prince-Arthur:
- reconstruction of water and sewer lines
- reconstruction of the Commission des Services Électriques de Montréal (CSEM) manholes
- Bell massif
- relocation of signal poles
- construction of 2 sidewalk projections on Prince-Arthur
- addition of an island for the Bixi station and a universally accessible bus station on Saint-Urbain
- bike path work at the Saint-Urbain/Prince-Arthur intersection
The work site will be on winter break and will resume in spring 2025 between Avenue des Pins and Rue Prince-Arthur, with work on :
- pavement reconstruction
- paving, bicycle path and pavement markings
These works may be postponed or their duration extended due to weather conditions or other constraints.
Obstructions and work sites
Consult the Obstructions and work sites digital service to locate obstructions caused by this work site.
Documentation
Need help?
Contact us if you have questions.
Are you sure you want to leave this page?
This page is not available in English. You will be redirected to the English home page.