Boulevard de Pierrefonds and Boulevard Jacques-Bizard: New water mains
New pipes are currently added under Boulevard de Pierrefonds and Boulevard Jacques-Bizard in order to secure the area’s drinking water supply. This project is the continuation of the construction work carried out on Boulevard de Pierrefonds between Rue Riva-Bella and Rue Sainte-Anne in 2021 and 2022
This project aims to secure the drinking water supply in Dollard-des-Ormeaux and L’île-Bizard.
The replacement of valves in the water distribution system will also improve the reliability of drinking water management in Pierrefonds-Roxboro borough.
Access will be maintained at all times in most cases. To minimize traffic impacts, major intersections may be closed on some weekends, and excavation work will be kept to a minimum.
Everything you need to know about the project
When?
Start: Winter 2024
Duration: About 2 years
Where?
- Boulevard de Pierrefonds, between Rue Sainte-Anne and Boulevard Saint-Jean
- Boulevard Jacques-Bizard, between Boulevard de Pierrefonds and Boulevard Gouin
Why?
Provide enough drinking water for homes, businesses, industries and fire hydrants, at sufficient water pressure.
Why do we do it?
To ensure a sufficient quantity and pressure of water to supply drinking water to homes, businesses, industries and fire hydrants.
Active work sites
Boulevard de Pierrefonds, at the intersection of Rue Paiement
Planned date: April 28
Estimated duration: 7 weeks
Traffic
- Boulevard de Pierrefonds: partial closure on eastbound lane at the intersection of Rue Paiement. At all times, at least one eastbound traffic lane will be accessible.
- Rue Paiement will become a dead-end south of boulevard de Pierrefonds.
Boulevard de Pierrefonds, west of Boulevard Saint-Jean
From May 12 to May 22
- Complete closure of the eastbound lane and closure of the right-turn lane towards Boulevard Saint-Jean southbound.
- Contraflow traffic in the westbound lane. At least one traffic lane in each direction will be maintained at all times.
From May 23 to May 25
- Boulevard Saint-Jean : complete closure at the intersection of Boulevard de Pierrefonds.
- Boulevard de Pierrefonds : complete closure of the eastbound lane and closure of the right-turn lane towards Boulevard Saint-Jean southbound.
- Contraflow traffic in the westbound lane. At least one traffic lane in each direction will be maintained at all times.
From May 26 to June 4
- Boulevard Saint-Jean northbound: obstruction at the intersection of Boulevard de Pierrefonds.
- Boulevard de Pierrefonds : complete closure of the eastbound lane.
- Contraflow traffic in the westbound lane. At least one traffic lane in each direction will be maintained at all times.
Documents
Virtual information session
Quick search
Need help?
Contact us if you have questions.
Are you sure you want to leave this page?
This page is not available in English. You will be redirected to the English home page.